AWS D1.1 is the Structural Welding Code for steel. For structural steel projects that require AWS D1.1 compliance, stud welding is covered under the stud welding portion of the code. This page is a plain-English overview. Always follow the current project specifications, the applicable AWS D1.1 edition, the engineer of record, and the inspector's requirements.
Not every stud welding job is an AWS D1.1 structural job. Signs, sheet metal, insulation pins, panels, and non-structural CD welding work may follow different project requirements.
A WPS (Welding Procedure Specification) is the written procedure for how the weld will be made. It typically includes stud type and diameter, base material, welding position, equipment, polarity, amperage, time setting, lift, plunge, ferrule type, preheat requirements, and testing requirements.
A PQR (Procedure Qualification Record) documents test results used to qualify a welding procedure when qualification is required. Simply put: the WPS tells the crew how to weld. The PQR proves that a procedure was tested and qualified when required.
Preproduction testing is commonly used to confirm that the stud, ferrule, base material, equipment, settings, and operator technique are producing acceptable welds before full production begins.
Production inspection may include visual inspection, bend testing, torque testing, tension testing, macroetch testing when required, and other project-specific testing. The exact inspection method should be confirmed with the project specification and inspector.
Bend testing is commonly used for headed studs because the stud can be bent to check weld soundness. For threaded studs, DBAs, or other studs that are difficult to bend without damaging the product, torque testing, tension testing, or another approved test method may be used when required by the project.